Turnkey Project : Nigeria – COLEMAN CABLE
Middle Voltage Cable Plant
Total Value: USD 9,800,000.00
Overview:




Main Products:
| TYPE | CROSS SECTION |
| WIRING CABLE | 1 to 5 cores 0.5—6mm2 |
| WIRING CABLE | 1to 5 cores 1.5-16mm2 |
| CONTROL CABLE | 2 to 19 cores 0.20—6 mm2 |
| FLEXIBLE CABLE | 10~400mm2 |
| CONTROL CABLE | 2 to 61 cores 0.5—240mm2 |
| FLEXIBLE CABLE | 120~400mm2 |
| LOW-VOLTAGE CABLE | 1 to 5 cores , 25-120mm2 ,unarmoured |
| LOW-VOLTAGE CABLE | 1 to 5 cores, 150-400mm2 ,unarmoured |
| AERIAL CABLE | 6.0-1000mm2 |
| LOW-VOLTAGE CABLE | 1 to 5 cores, 1.5-400mm2, armoured |
| MIDDLE VOLTAGE CABLE | 1 to 3 cores, 6-35KV、25-800mm2 |
Layout Design:

Supply Service List:
| Service list | Quantity | Year |
| The whole Solution for design; | 1 | 2012.6-2012.8 |
| 11KV-35KV CCV LINE(EPC PROJECT) | 2 | 2012.1 |
| Stranding machine: 630/37 | 2 | 2012.1 |
| Stranding machine: 630/61 | 2 | 2012.1 |
| Tubular stranding machine: 630/1+6 | 2 | 2012.1 |
| Tubular stranding machine: 1* 1250+12*630 1 set; | 1 | 2012.1 |
| 1250mm laying up machine | 1 | 2012.1 |
| 2500 drum twister with armoring machine | 1 | 2012.1 |
| High voltage shielding room; | 1 | 2012.1 |
| JTGN-50KVA/5KV/20KV AC test system | 2 | 2012.1 |
| Crane: 10T; 22m | 2 | 2013-2014 |
| Crane: 10T; 28m | 2 | 2013-2014 |
| 90 extruder machine,120+100;120+150 extruder machine | 6 | 2013-2014 |
| Light and light fittings | 1000 units | 2013-2014 |
| Electrical fittings | 4 containers | 2013-2014 |
| Air compressor and system | 8 | 2013-2014 |
| PSA Nitrogen unit | 1 | 2013-2014 |
| Cooling tower and cooling water system | 5 | 2013-2014 |
| Forklift: 5 tons | 2 | 2013-2014 |
| Forklift: 7 tons | 2 | 2013-2014 |
| Sweeper | 12 | 2014 |
| Crane truck: 12 tons | 1 | 2014 |
| Crane truck: 16 tons | 1 | 2014 |
| Maintenance machine: lathe; drilling machine, milling machine, shaper machine | 8 | 2014 |
| Woodworking machines: band saw; drilling machine | 6 | 2014 |
| Shielded cables | 10 drums | 2014 |
| Cable tray | 2000m | 2014 |
| Loadometer: 10 tons | 2 | 2014 |
| Welding machine | 100 | 2014 |
| Factory fans | 200 | 2014 |
| Installation tools | 6 sets | 2014 |
| Project management | 12 months | 2014.1-2014.12 |
| Installation | 4 months | 2014.5-2014.10 |
| Commissioing and tesing | 2 months | 2014.10-2014.12 |
| Training and production supervision | 2 months | 2015.1-2015.2 |